Comments?

Email

e-princerupert.com

Prince Rupert Regional Information Site

NATURE

Sea, land, river

PEOPLES

Community

 

 

 


For earlier materials see
Table of Contents

March 15th

We See

3 sewage treatment plants

When I took the picture assumed this was wind damage – but when asked City Staff (the tarp etc would have needed cleaning up, etc) --- was told probably removed by owner to prevent all those pigeon droppings – by removing their shelter

 

 

Above is from the Public sessions Thursday

Public Sewage Treatment meetings

The first day the various proposals and back ground material shown to public in general – the 2nd day was committee discussion with various ‘Reps’ from City, Port, Business etc – while I was not given ‘permission’ to speak for PRES (by the 4 members attending their last meeting) –still I was allowed Friday to speak from a broader Environmental perspective

 

The first option was one large treatment plant at Hays Creek

The second option was 2 smaller plants at Hays and Morse

The third option was 3 smaller plants at Hays, Morse and Seal Cove

Tactically the 3rd option gives us more freedom to adapt to future changed circumstances

Here is the option chosen

The colored lines are present sewage lines along with ‘outfalls’ (example Outfall I at red arrow—by far the longest and the deepest)

 

Given the Rupert’s present financial situation – building a sewage treatment plant is not in the immediate future --- but can work towards that future now that we have a clear sense of where going (see below)

 

Why 3?

Some at meeting argued for one large treatment facility at Hays Creek – the present outfall I is adequate – plus one site arguably ‘cheaper’ and more efficient--- Others countered the 3 site option gave us more flexibility and allowed City to phase in sites as $$ etc became available --- thus the first treatment plant would be built at Hays – and if we changed are minds later it could be expanded to treat all the cities needs ---- Seal Cove would be last site to be built – and it could accommodate all those as yet un-built suburbs (see pink arrow above)

Culmination for Retiring Bob Thompson

Bob recounted how this ‘file’ was opened for him in 1971 when he had the money etc to extend the main sewer outfalls deeper into harbour --- but the Council of the day decided that need not spend the $$ as the project went well beyond the receiving waters regulations of the day --- and now 40 years later he is finally seeing what will be needed and what will ‘satisfy’ today’s regulations

--------------------------------------------------------------------

Costs? – Surprisingly all 3 sites cost about the same: 122M$ --- nor would the operation costs for one large versus 3 smaller be that much different according to consultants

 

My Previous on Sewage in Harbour etc

PR Sewage Treatment? Harbour System is complex (geography)
And in 2003 a good computer simulation published (story)
Here is an earlier study where 'Friends of Harbour' question outfalls 
And a much earlier journalism article where 'disaster scenario' for dilution solution

 

 

Galaxy Gardens has made excellent use of the ‘iron curtains’ as design etc

More later on downtown buildings and rejuvenation etc

 

 

 

 

 

 

 

 

 

Created by LG on 15/3/2010

Last updated on Monday, March 15, 2010